How aluminium facade panels are installed
Installation follows a fixed order: survey the structure as built, set out and level the substructure, fix brackets and rails, hang panels in numbered sequence, then set joints and inspect. The survey matters most, because the gap between the drawn structure and the built structure is what the bracket adjustment has to absorb. Panels are hung from the bottom up or in the sequence the setting-out drawing specifies, so joints stay consistent across the elevation.
Key points
- Survey the structure as built before fixing anything; brackets absorb the difference from the drawing
- Level and align the substructure first, since panel alignment can only be as good as the rails
- Hang panels in the numbered sequence given on the setting-out drawing
- Set and check joint widths as work proceeds rather than correcting at the end of the elevation
The values below are the ones the factory publishes for this range. Anything outside them is quoted against your drawing rather than assumed.